  • Monitoring of the ESHS management plan implementation
  • Project management
  • Assistance in tendering (tender documents, clarifications, bid evaluation, contract award)
  • Assistance in implementing environmental and social measures
  • Supervision of construction and commissioning of 400/110 kV substation Ohrid
  • Supervision of construction and commissioning of the 400 kV substation Bitola 2 extension
  • Supervision of construction of the new 400 kV line Bitola 2 – Ohrid – Albanian border
  • Specification, tendering and supervision of a smart grid forecast system for renewables
  • Support in legal issues

CLIENT

AD MEPSO

DONOR

EBRD

DURATION

2019-2022

CONTRACT VALUE

EUR 1.9 M