Procurement and Project Management for 55 Substations between 6 kV and 1150 kV  

Services provided

  • Preparation of tender documents for a partial refurbishment of 55 substations, preparation of technical specifications
  • Assistance at the pre-qualification stage, evaluation of bids
  • Supervision of turn-key contracts: review of design documentation, supervision of Contractors’ works
  • Project coordination, training

CLIENT

Kazakhstan Electricity Grid Operating Company (KEGOC)

DONOR

ERBD

DURATION

2008-2013

CONTRACT VALUE

EUR 2.3 M