Consulting Services for the Technical and Environmental Supervision of Seven Projects for the Reinforcement of Substations and Transmission Lines of 138 kV and 230 kV

Services provided

  • Review of tender documents for substations Terrabona and El Cua
  • Review of design documents presented by the Contractor
  • Assistance in factory acceptance tests of equipment
  • Supervision of Contractors’ construction works
  • Budget control
  • Administration of contract(s) with the Contractor(s)
  • Follow-up of technical and environmental standards
  • Reporting

CLIENT

Empresa Nacional de Transmisión Eléctrica (ENATREL)

DONOR

IDB

DURATION

2016-2019

CONTRACT VALUE

USD 3.1 M